<?xml version="1.0"?>
<!--<!DOCTYPE nitf SYSTEM "nitf-3-4.dtd">-->
<nitf>
  <head>
    <title id="Title"></title>
    <docdata management-doc-idref="">
      <date.issue id="CreationDate" norm="" />
      <du-key id="rev-ver" generation="1" version="Default" />
      <du-key id="Parent-Version" version="" />
      <identified-content>
        <classifier id="newspro-nitf" value="r2" />
        <classifier id="Newspro-App" value="Epaper" />
        <classifier id="Content-Type" value="Story" />
        <classifier id="storyID" value="93775" />
        <classifier id="CmsConID" value="" />
        <classifier id="Desk" value="" />
        <classifier id="Source" value="" />
        <classifier id="Edition" value="" />
        <classifier id="Category" value="-1" />
        <classifier id="UserName" value="" />
        <classifier id="PublicationDate" value="03/03/2021" />
        <classifier id="PublicationName" value="DailyStar" />
        <classifier id="IsPublished" value="Y" />
        <classifier id="IsPlaced" value="Y" />
        <classifier id="IsCompleated" value="N" />
        <classifier id="IsProofed" value="N" />
        <classifier id="User" value="" />
        <classifier id="Headline-Count" value="" />
        <classifier id="Slug-Count" value="0" />
        <classifier id="Photo-Count" value="0" />
        <classifier id="Caption-Count" value="0" />
        <classifier id="Word-Count" value="0" />
        <classifier id="Character-Count" value="0" />
        <classifier id="Location" value="" />
        <classifier id="TemplateType" value="1" />
        <classifier id="StoryType" value="Story" />
        <classifier id="Author" value="" />
        <classifier id="UOM" value="mm" />
        <classifier id="kicker" value="" />
        <classifier id="ByLine" value="" />
        <classifier id="DateLine" value="" />
        <classifier id="box-geometry" value="351,1182,814,1548" />
      </identified-content>
      <urgency id="home-page" ed-urg="0" />
      <urgency id="priority" ed-urg="0" />
      <doc-scope id="scope" value="0" />
    </docdata>
    <pubdata type="print" name="DailyStar" date.publication="20210303T000000+5.30" edition.name="Main Edition" edition.area="MAI" position.section="DST03032102MAI-NEWS" position.sequence="2" ex-ref="DST03032102MAI-NEWS.indd" />
  </head>
  <body>
<body.head>
      <hedline>
    	<hl1 id="Headline1" class="1" style="Headline1">
		<lang class="3" style="Headline1"  font="ITC Giovanni Std"  size="27">Some coping better than others </lang>
	</hl1>

       </hedline>
</body.head>
    <body.content id="Bodytext" CaptionAsBody="0">
     <block>
	<media id="1" media-type="image">
			</media>
</block>

     <p style=".Bodylaser">
	<lang class="3" style=".Bodylaser" font="ITC Giovanni Std" fontStyle="Bold">FROM PA1GE 1
</lang>
</p>
<p style=".Bodylaser">
	<lang class="3" style=".Bodylaser" font="ITC Giovanni Std" fontStyle="Book">all these projects are complete.
</lang>
</p>
<p style=".Bodylaser">
	<lang class="3" style=".Bodylaser" font="ITC Giovanni Std" fontStyle="Bold">ADP REVISION</lang>
<lang  class="3" style=".Bodylaser" font="ITC Giovanni Std" fontStyle="Book">
</lang>
</p>
<p style=".Bodylaser">
	<lang class="3" style=".Bodylaser" font="ITC Giovanni Std" fontStyle="Book">Bangladesh Railway (BR) is implementing the Padma Bridge Rail Link Project to connect the capital to Jashore with a 169km rail line over the under-construction Padma bridge at a cost of Tk 39,246 crore.
</lang>
</p>
<p style=".Bodylaser">
	<lang class="3" style=".Bodylaser" font="ITC Giovanni Std" fontStyle="Book">China Railway Group Ltd, the contractor for the biggest project of BR, issued a press statement on February 24 alleging that it had not been paid for work done in the last seven months and this was slowing down project implementation.
</lang>
</p>
<p style=".Bodylaser">
	<lang class="3" style=".Bodylaser" font="ITC Giovanni Std" fontStyle="Book">The contractor claimed that the government owes it $400 million and the payment delay rendered it unable to buy sufficient construction materials and pay subcontractors and suppliers timely.
</lang>
</p>
<p style=".Bodylaser">
	<lang class="3" style=".Bodylaser" font="ITC Giovanni Std" fontStyle="Book">The project authorities itself told a railway meeting on February 9 that they were facing fund problems. They sought Tk 1,801.14 crore from the ADP on November 25 but did not get it as of February 9, read BR documents.
</lang>
</p>
<p style=".Bodylaser">
	<lang class="3" style=".Bodylaser" font="ITC Giovanni Std" fontStyle="Book">According to the revised ADP documents, the annual allocation for the project was Tk 3,684.36 crore but it has been revised to Tk 5,454.86 crore.
</lang>
</p>
<p style=".Bodylaser">
	<lang class="3" style=".Bodylaser" font="ITC Giovanni Std" fontStyle="Book">Contacted, Project Director Golam Fakhruddin Ahmed Chowdhury said the revised allocation would help them overcome the situation.
</lang>
</p>
<p style=".Bodylaser">
	<lang class="3" style=".Bodylaser" font="ITC Giovanni Std" fontStyle="Book">“Actually, we wanted to speed up the project work. So we need more allocation,” he said.
</lang>
</p>
<p style=".Bodylaser">
	<lang class="3" style=".Bodylaser" font="ITC Giovanni Std" fontStyle="Book">Padma Bridge Rail Link project witnessed 37.39 percent overall progress until January.
</lang>
</p>
<p style=".Bodylaser">
	<lang class="3" style=".Bodylaser" font="ITC Giovanni Std" fontStyle="Book">The Tk 35,984 crore Matarbari power plant is scheduled to be completed by 2023. The original ADP allocation of Tk 3,672 crore for the project was revised to Tk 4,200 crore.
</lang>
</p>
<p style=".Bodylaser">
	<lang class="3" style=".Bodylaser" font="ITC Giovanni Std" fontStyle="Book">Another project that got additional allocation is the Payra Deep-sea Port project. The original allocation for the project this fiscal year was Tk 700 crore but it would now get Tk 1,151.67 crore.
</lang>
</p>
<p style=".Bodylaser">
	<lang class="3" style=".Bodylaser" font="ITC Giovanni Std" fontStyle="Book">After the first revision, the project cost rose to Tk 4,516.75 crore and completion deadline was re-fixed to June 2023, one and half years more than the original.
</lang>
</p>
<p style=".Bodylaser">
	<lang class="3" style=".Bodylaser" font="ITC Giovanni Std" fontStyle="Book">While approving the revision on February 16, the PM directed Payra Port Authority (PPA), the implementing agency, to prepare a detailed work plan involving the government’s development agenda.
</lang>
</p>
<p style=".Bodylaser">
	<lang class="3" style=".Bodylaser" font="ITC Giovanni Std" fontStyle="Book">Allocation for the 2,400MW Rooppur Nuclear Power Plant, the biggest single project which is worth Tk 1,13,092 crore, witnessed significant reduction.
</lang>
</p>
<p style=".Bodylaser">
	<lang class="3" style=".Bodylaser" font="ITC Giovanni Std" fontStyle="Book">The project would now get Tk 10,166.78 crore this fiscal, which is Tk 5,524.35 crore less than the original allocation.
</lang>
</p>
<p style=".Bodylaser">
	<lang class="3" style=".Bodylaser" font="ITC Giovanni Std" fontStyle="Book">The power plant project made 34.34 percent progress until December last year.
</lang>
</p>
<p style=".Bodylaser">
	<lang class="3" style=".Bodylaser" font="ITC Giovanni Std" fontStyle="Book">Annual allocation for Padma bridge reduced to Tk 2,099.93 crore. The original allocation was Tk 5,000 crore.
</lang>
</p>
<p style=".Bodylaser">
	<lang class="3" style=".Bodylaser" font="ITC Giovanni Std" fontStyle="Book">Apart from the pandemic, the much-hyped project faced huge challenge due to strong currents in the Padma river. No span could not be installed for around four months due to this, officials said.
</lang>
</p>
<p style=".Bodylaser">
	<lang class="3" style=".Bodylaser" font="ITC Giovanni Std" fontStyle="Book">However, installation of the all spans were completed in December last year and the bridge is expected to be opened to the public in June next year.
</lang>
</p>
<p style=".Bodylaser">
	<lang class="3" style=".Bodylaser" font="ITC Giovanni Std" fontStyle="Book">The overall implementation progress of the project is 84 percent as of January.
</lang>
</p>
<p style=".Bodylaser">
	<lang class="3" style=".Bodylaser" font="ITC Giovanni Std" fontStyle="Book">Allocation for the Chattagram-Cox’s Bazar rail line project was cut to Tk 990 crore from the original Tk 1,500 crore.
</lang>
</p>
<p style=".Bodylaser">
	<lang class="3" style=".Bodylaser" font="ITC Giovanni Std" fontStyle="Book">Project work suffered delays due to the pandemic, that’s why the funds could not be utilised, a project official said.
</lang>
</p>
<p style=".Bodylaser">
	<lang class="3" style=".Bodylaser" font="ITC Giovanni Std" fontStyle="Book">The project has seen 49 percent progress as of January.
</lang>
</p>
<p style=".Bodylaser">
	<lang class="3" style=".Bodylaser" font="ITC Giovanni Std" fontStyle="Book">The MRT-6, an elevated metro rail from Uttara third phase to Motijheel, saw 56.94 percent overall progress made as of January.
</lang>
</p>
<p style=".Bodylaser">
	<lang class="3" style=".Bodylaser" font="ITC Giovanni Std" fontStyle="Book">Annual allocation for the project, Tk 5542.83 crore, remained unchanged.